Owner of Amazon Warehouse Land Takes North Myrtle Beach Drone Pad Denial to Court

The owner of the land under Amazon's warehouse in North Myrtle Beach, South Carolina, has appealed in court the city planning commission's refusal of a drone launch pad. The commission voted 6-0 against it on October 20.

Foto: DroneXL

A Delaware statutory trust, ExchangeRight Essential Income 11 DST, which owns the land under Amazon's delivery warehouse in North Myrtle Beach, South Carolina, filed a 12-page appeal on November 19 in the Horry County Court of Common Pleas. The appeal targets the city planning commission's October 20 decision to refuse a drone launch and landing pad on the site. The trust also asked for pre-litigation mediation, The Post and Courier reported. If approved, the pad would be Amazon's first drone delivery site in South Carolina.

What was rejected

The proposed pad is a 13,627-square-foot (about 1,266 square meter) paddock behind the existing building at 8651 Water Tower Road. The commission voted 6-0 to deny it, with one member absent. Its findings cited resident noise complaints in Richardson and College Station, Texas, and described them as evidence of potential impacts, not proof the same would occur in North Myrtle Beach. The commission called the distances to homes, about 366 meters to planned ones and 671 meters to existing ones, favorable.

The appeal's arguments

According to the newspaper's account of the filing, the trust says the city had no site-specific study, expert testimony or measured data showing incompatibility with the surrounding industrial uses. It asks a judge to reverse the denial or return the application to the commission. City planners had warned in writing that a denial should rest on supported impacts rather than predictions or general opposition.

What happens next

South Carolina law requires mediation to be granted when requested. Any settlement takes effect only after City Council approval in public session and approval by a judge, and it applies only to this parcel. If mediation fails, the owner has 30 days to file a full petition.

Approving the site plan would not by itself authorize flights, which would still depend on Federal Aviation Administration (FAA) authorization.