LatviaPublished: 19 November 2026 at 05:03

Declassified report: Rail Baltica first-stage costs may be twice as high

A declassified government report says independent consultants estimate the first-stage costs of the Rail Baltica railway project at double what was previously assumed. The consultants conclude the project cannot be delivered in Latvia under its current scope, governance and financing.

Foto: Žurnāls Ir

A government information report on the Rail Baltica railway project, which ministers reviewed in a closed session in early October, has now been declassified. It states that experts from the international financial and management consulting firm Alvarez&Marsal calculate the first-stage costs of Rail Baltica at twice the level assumed until now. This matters because the assessment is to serve as the basis for further decisions on how the project proceeds in Latvia.

Conclusion on feasibility

The consultants reached a stark conclusion: under its existing scope, governance model and financing framework, Rail Baltica is not feasible in Latvia. Their in-depth assessment, according to the report, will underpin the government's next decisions. The assessment itself remains confidential.

A new office for oversight

There are plans to set up a new office to oversee the project, which would report to the prime minister.

How the assessment came about

Latvijas Dzelzceļš, the Latvian railway company, commissioned the Alvarez&Marsal assessment last summer on the instruction of the government led by Evika Siliņa (JV). The information report was also kept secret for a long time, but it was declassified after persistent interest from journalists.

The source also notes that construction of the main-line embankment continued in October in the southern section of the route in Latvia, near Iecava.