RegionsPublished: 22 November 2026 at 07:04

Bauska Hospital Opens Renovated Admissions Unit and Day Clinic After 22-Month Rebuild

Bauska Hospital in Latvia opened its renovated admissions department and a new day-care unit on 20 November. The rebuild of the inpatient building took 22 months and cost about 4.09 million euros including VAT.

Foto: Bauskas Dzīve

Bauska Hospital, a municipally owned facility in southern Latvia, held a ribbon-cutting on Friday, 20 November, for its renovated admissions department on the ground floor and a new day-care unit on the second floor. About 40 staff members and guests attended. The event marked the end of a 22-month reconstruction of the hospital's inpatient building, during which the hospital operated in temporary premises.

Hospital head Margarita Epermane thanked employees and partners for their resilience and responsiveness during the works. She said the building now has modern ventilation that will maintain a good indoor climate in patient rooms, care areas and operating rooms. A new lift has also been installed, allowing patients to be transported between floors in beds. Chief physician Inese Strazda highlighted the mutual support among staff while they worked in more cramped conditions.

Speeches were also given by the head of the admissions department, Roberts Škapars, Bauska municipality council chairman Aivars Mačeks, and representatives of SEB bank, which financed part of the renovation. Epermane said the refurbished facilities should help provide quality state-funded and paid services to local residents. She noted that young medical staff will be able to develop their skills in good conditions, and mentioned a plan to develop medical tourism.

What has changed

The emergency medical care and admissions department was renovated on the first floor. On the second floor, a day-care unit was created with an operating block and two operating rooms. A new lift was built, and ventilation, heating and internal utility systems were renewed.

Costs and timeline

The rebuild was initially planned at 2.4 million euros, with the contract signed in January 2025. In spring, additional funding was needed: SEB bank granted a loan of 1.348 million euros to repair structural damage discovered during construction in the oldest part of the building, which is about 180 years old. As a result, the construction deadline was extended to the end of August.

Total costs are 3,381,493.62 euros excluding VAT, or 4,091,607.28 euros including VAT. Construction was carried out by SIA LVS Building, while design and author supervision were handled by the architecture firm SIA OZOLA & BULA. At the end of the ceremony, hospital staff were presented with commendation certificates from the municipality and the hospital.