All lanes on Daugavpils highway in Ikšķile to reopen for winter

All lanes in both directions will reopen on the Daugavpils highway (A6) reconstruction section in Ikšķile during the winter break, though speed limits will remain. Construction is due to resume in spring 2027 and finish by August.

Foto: Delfi

State-owned company Latvijas valsts ceļi (LVC), which manages Latvia's state roads, says all lanes in both directions will be opened to traffic on the Daugavpils highway (A6) reconstruction section near Ikšķile, in Ogre municipality, during the winter pause in works. Depending on the weather, traffic arrangements are to change from Saturday, 21 November. The works are not finished and not all the necessary equipment has been installed, so speed limits will stay in place.

What changes for drivers

Traffic will be restored on both carriageways, separately toward Riga and toward Ogre. At the Skolas iela junction, ramps on both sides of the highway will open, allowing travel to and from Ikšķile. At the Elkšņu junction, the ban on left turns for vehicles arriving from the Ogre side will be lifted.

Heading from Riga toward Ogre, the maximum speed will be 70 km/h up to Daugavas prospekts and 90 km/h beyond it. In the opposite direction the limits will be 90 km/h and then 70 km/h. On the ramps to Ikšķile the limit will be 50 km/h. Public transport stops will be in their permanent locations on the ramps at the Skolas iela junction.

Pedestrian tunnels

The Priežu and Egļu iela tunnel will open to pedestrians, while the Stacijas iela and Daugavas prospekts tunnels will remain closed. LVC urges people to follow the road signs and markings on site.

Scope of work and next steps

Since July, a two-kilometre stretch of the highway's asphalt surface has been rebuilt, with new drainage and storm sewerage; three asphalt layers and safety barriers are to be added at the end. Three tunnels under the highway are also being renovated. In the Daugavas prospekts tunnel, the main water pipe has been relocated and a storm sewer pumping station is being built; video surveillance will be installed next year.

About half of the work on the combined pedestrian and cycle path from Ikšķile to Ogre has been completed. In 2027, a noise barrier 2.7–3.5 metres high will be installed on both sides of the road between Īsā iela and the Ikšķile skatepark.

The contractor is SIA "ACBR", with a contract value of 11,131,989.34 euros including VAT. Construction supervision is provided by SIA "ACM Projekts".