Great Guild's Great Hall takes new shape as acoustic works continue

In the reconstruction and restoration of the Great Guild, led by state real estate company VNĪ, work continues on the Great Hall's ceiling and acoustics. Total project costs are planned at about 17.3 million euros.

Foto: BNN

Valsts nekustamie īpašumi (VNĪ), the Latvian state-owned company that manages government property, is continuing the reconstruction and restoration of the Great Guild building. The Great Guild is an architectural monument of national significance and home to the Latvian National Symphony Orchestra. The Great Hall is now taking on a new outline, and the restored end wall of the hall plays an important role in its acoustic solutions.

Progress of the works

The first stage of construction, focused on improving energy efficiency, was fully completed in June. It included rebuilding internal utility networks, insulating roofs and replacing roofing, and restoring windows and doors.

Currently, the installation of metal ceiling structures in the Great Hall and the construction of acoustic solutions are under way. Alongside this, crews are building internal low-voltage networks and new partition walls, as well as carrying out interior finishing and restoration work.

Contractor's financial difficulties

VNĪ board member Jeļena Gavrilova says the company responded in good time to reports of the builder's financial difficulties. Additional resources have been assigned to step up oversight of the project and the contractor, and contract performance risks have been assessed in depth. According to her, this makes it possible to find solutions quickly, keep work continuous and protect the client's interests.

Funding

The Ministry of Culture secured 10.4 million euros for the project from the European Union's 2021–2027 cohesion policy programme. The Ministry of Economics attracted a further 6.3 million euros from the Recovery and Resilience Facility plan for energy efficiency investments in public sector buildings. In total, about 17.3 million euros are planned to be invested.

What else is planned

The reconstruction is set to rebuild the Great Hall's stage, audience seating and ceiling structures, and to improve accessibility. Historic wooden windows and doors will be restored, the roof insulated, and the water, heating, ventilation, electrical and low-voltage networks rebuilt. Changes are also expected in the basement, where visitor restrooms and the cloakroom will be rebuilt, while some rooms will be adapted for administration and musicians.