NextDC to keep future datacentres away from homes after Melbourne community backlash
Australian datacentre operator NextDC says it will no longer pursue new developments near residential properties, after community protests in Melbourne delayed an expansion and its share price fell 40%.

Australian datacentre operator NextDC has said it will no longer pursue new developments near homes, following community opposition in inner Melbourne that sent its share price down 40%. The company announced the change at its annual general meeting on Friday.
The dispute centres on the expansion of NextDC's M3 datacentre in West Footscray. Power provider Jemena paused construction of new 22-metre power poles after community protests, forcing NextDC to delay the project. The share price has since recovered to more than $9, but in the meantime rival Goodman Group acquired a stake of nearly 10% in the business.
Shareholder discontent
At the meeting, shareholders issued a second strike against executive pay, but a motion to spill the board was resoundingly defeated on Friday. Chief executive Craig Scroggie called it his hardest AGM in 15 years and said management takes responsibility for community support, among other things. He acknowledged that residents should have been heard earlier and that the company needed to work more closely with its power and construction partners.
Promised changes
NextDC will set up a new community consultative committee, including a standing forum for residents and local stakeholders. Each project will have a dedicated website and contact channels with defined response times for complaints and inquiries.
Chair Doug Flynn said that, given community sensitivities, the company does not intend to pursue new developments near residential properties. He added that the M3 site had been industrial land for 100 years, with petrochemical works there before the datacentre was built.
Flynn also said the Jemena employee overseeing community engagement had left the business. A Jemena spokesperson declined to comment but pointed to a September statement saying its general manager for electricity networks had decided to step down.