Paris-based HoloSolis raises over €15 million for solar panel gigafactory in France
French solar manufacturing startup HoloSolis has closed a Series A funding round of more than €15 million. The money will prepare the ground for a gigafactory whose total cost is estimated at about €1 billion.
HoloSolis, a Paris-based solar equipment manufacturing startup, has closed a Series A investment round raising more than €15 million. The funds are earmarked for preparing a solar panel gigafactory planned in northeastern France. The project matters for Europe because it could reduce reliance on imported solar panels, most of which come from outside the continent; the European Union regards this dependence as a vulnerability for its energy security.
Who invested
Four new investors joined the round: the Crédit Agricole banking group (through four of its regional banks), investment firm Algebris, solar panel maker Trina Solar and EV charging infrastructure company StarCharge. They were joined by existing backers Calès Technologies, Forming and Ecolab. In November 2025 the company had already secured more than €220 million in public and private funding. Total financial support identified for the project now exceeds €400 million.
HoloSolis CEO Henri Poupart-Lafarge said the confidence of the new shareholders, together with backing from French and European public authorities, allows the company to move forward with confidence to the next stages of developing and financing the factory.
About the company and the plant
HoloSolis was founded in 2022 by InnoEnergy, a European cleantech investor and company builder. It is one of five industrial companies launched by InnoEnergy, alongside battery maker Verkor, hydrogen producer FertigHy, green-steel startup GravitHy and energy-storage company Repono.
The factory is to be built in Hambach, in the Moselle department. On a single 50-hectare site, the company plans to automate both the manufacture of photovoltaic cells and their assembly into solar modules. Products will use n-type TOPCon technology, one of the most efficient solar cell architectures currently available.
The total investment is estimated at about €1 billion. At full capacity, the plant would produce 5 GW of panels a year, roughly 10 million panels, and create 2,000 direct jobs. Construction is planned to begin in 2028, with production due in 2029. France has designated the project as one of major public interest, and the European Commission has recognised it as a strategic “Net Zero” project. The company has also been shortlisted for a grant from the Commission’s Innovation Fund.
What comes next
Series A proceeds will pay for pre-construction work: detailed engineering studies, technical specifications, selection of production-line suppliers and qualification of panel prototypes. The company already holds letters of intent covering more than 30 GW from prospective customers. Its main focus now is converting these into binding agreements and completing its next fundraising round, expected to open in the coming months.