Reconstruction of Tirgus Street begins in Pāvilosta
Reconstruction work has begun on Tirgus Street in Pāvilosta, including new asphalt and cobblestone paving. The project is due for completion by November 30.

Reconstruction work has begun on Tirgus Street in the town of Pāvilosta. The project involves laying around 400 meters of asphalt concrete surface along with roughly 50 meters of cobblestone paving. The section under construction runs from Smilšu Street to the access road leading to the sea.
The works are scheduled to be completed by November 30 of this year.
Funding
The total cost of the project amounts to 353,259.50 euros. The largest share, 233,098.42 euros, is being covered by the European Maritime, Fisheries and Aquaculture Fund (EMFAF). The remaining 120,161.08 euros is financed by the South Kurzeme municipality.