Costlier platform works in Vidzeme leave Liepāja and Dobele without funding
Latvian state railway company Latvijas dzelzceļš halted in September a tender to rebuild platforms in Liepāja and Dobele after construction cost increases elsewhere drained the budget. The same tender is also tied to an anti-corruption investigation into an alleged bribe offer.

Latvian state railway company Latvijas dzelzceļš stopped a tender in September for rebuilding station platforms in Liepāja and Dobele because the money ran short. According to the Latvian Television programme De facto, the funds were absorbed by higher construction costs on the Rīga–Lugaži–state border line in the Vidzeme region. The platform modernisation is co-financed by European funds, and unfinished works are already affecting passengers.
Setbacks on the Aizkraukle line
Latvijas dzelzceļš launched the project five years ago. New platforms in Rīga, Jelgava, Tukums and elsewhere were initially budgeted at 44 million euros and were meant to be ready in 2023. Works were delayed and became more expensive, and at 12 stops on the Aizkraukle line passengers are still waiting. Construction was entrusted to a partnership of the companies BMGS and Fima Group. In February this year BMGS became insolvent, and soon afterwards Latvijas dzelzceļš terminated the contract. Patriks Markēvičs, director of the Railway Department at the Ministry of Transport, said the platform projects had become stuck, and the ministry added that Latvijas dzelzceļš also failed to monitor contract performance in time.
The next round and Liepāja with Dobele
The next round is to build new platforms at another 22 stations and stops, nine of them on the Rīga–Lugaži–state border line. Fima, which submitted the cheapest bid, was excluded for violations, and the Procurement Monitoring Bureau found that decision justified. The second-best bidder, Belam–Rīga, received a negative opinion from the Constitution Protection Bureau, so no contract has been signed. If a third bidder must be chosen, costs would rise by 2.5 million euros including VAT. Results are expected in December.
For the Liepāja and Dobele works, the CHR–UPTK consortium had been selected in summer with a bid just under three million euros. It has challenged the termination at the Procurement Monitoring Bureau and expects a ruling next week. The platforms are still planned to be finished by the end of 2029; early next year a new tender, for design only, is planned at up to 300 thousand euros.
Bribery suspicion
The Liepāja line tender came to the attention of the Corruption Prevention and Combating Bureau (KNAB) last autumn. Investigators suspect that someone offered a 20,000-euro bribe to an adviser to the Latvijas dzelzceļš board so that a certain group of companies would not be excluded from the tender. KNAB has completed its investigation and asked prosecutors to start criminal proceedings. According to De facto, it was most likely offered in the interests of CHR–UPTK. The businesspeople categorically deny any involvement.