BalticsPublished: 17 November 2026 at 00:03

Professor: New power generation should accompany data center construction

Professor Landsberg says the large data centers planned in Estonia should secure additional electricity generation capacity so they do not push up prices for other consumers. He argues grid costs should not fall solely on other users.

Foto: ERR News

The impact of large data centers planned in Estonia on the electricity system and prices calls for new regulation, Professor Landsberg told Estonian public broadcaster ERR. He says developers should ensure additional generation capacity alongside their projects, so that the new demand does not raise market prices for existing consumers.

Demand compared with the system

Two data centers are planned in Estonia: one in Hüüru near Tallinn and another in Risti. Each is designed for roughly 200 megawatts. Estonia's peak demand in the highest-load hour of this past winter was about 1,700 megawatts, so a single such facility would account for more than 10 percent of it. Annually, it could use 1.3–1.6 terawatt-hours, or roughly 20–25 percent of Estonia's yearly consumption.

According to data from Elering, the electricity system operator, connection requests from data centers and other large consumers total around 3,000 megawatts. Landsberg notes that requests do not automatically become completed projects, and that data centers are usually built in phases.

Sharing the costs

The professor says data centers' consumption is steadier than that of many other users, which makes them valuable customers. However, fixed costs make up a growing share of system expenses. Household and commercial consumption in Estonia is rising while industrial consumption is falling, so fixed network costs are spread across fewer users. In his view, data centers should bear a larger share of grid investments.

New capacity and storage

Landsberg points to a change under discussion in Finland's parliament that would require data centers seeking grid connections to secure additional generation capacity on a long-term basis. This could mean building their own power plants or signing long-term agreements. The Risti project is planned together with solar and wind generation and battery storage.

Batteries can smooth fluctuations within and between days, but seasonal variation remains unresolved. For now, he says, there is no better option than fossil-fuel plants such as gas-fired ones. Over the longer term he sees a role for hydrogen.

Use of waste heat

Reusing waste heat depends on whether a large heat consumer is nearby. It should be easier to find one for Hüüru than for Risti. It requires extra investment and carries risks, so developers must weigh the benefits.