Preparatory work has begun at Riga Airport in Latvia for the expansion of its terminal, with 98 million euros earmarked for the project. Reconstruction of access roads and car parks starts in December, and from the middle of next year the way passengers reach the terminal will change significantly. The expansion will add 20,000 square metres to the terminal.
First stage: roads and car parks
The first construction stage, running from this December until September 2027, will include new access roads, adjustments to existing ones, and reworked public transport lanes and car parks. A construction site and the infrastructure needed for the works are already being set up on airport grounds.
Passengers will notice the biggest changes from mid-next year, when demolition of the current ramps to the second-floor departure hall begins. Vehicles will no longer be able to reach the terminal at second-floor level, and both car and passenger traffic will be confined to the ground floor. Temporary entrances and exits will be arranged, and new car parks and access roads will open.
The new terminal building
Construction of the new building is planned to start in autumn 2027 and finish by summer 2030. It will occupy part of the current short-term car park P1. The building will house a larger check-in hall, waiting areas, a security screening zone and a baggage claim hall.
Operations during construction
The airport stresses that it will keep operating as usual throughout the works, although passengers and visitors should expect traffic restrictions and changes to how they move around. Particular attention will be paid to keeping the airport accessible to people with mobility impairments. The public will be informed of upcoming changes in good time.
Contractors and financing
The expansion will be carried out by RIXLA, a joint venture of construction companies LNK Industries and Arčers. Construction costs are put at 98 million euros, financed by the European Bank for Reconstruction and Development, the Nordic Investment Bank and the Latvian branch of OP Corporate Bank. Additional funds are earmarked for modern passenger service and security technologies.