Tallinn to start €14M Pärnu Highway overhaul next summer
Tallinn, the capital of Estonia, plans to start a €14 million reconstruction of the central section of Pärnu mnt next summer. The work must be finished by 2029, and motorists should expect traffic changes.

Tallinn, the capital of Estonia, intends to begin a €14 million reconstruction of Pärnu mnt (Pärnu Highway), one of its main central thoroughfares, next summer. The city is warning drivers and commuters to expect significant traffic disruption. EU funding rules require the work to be completed by the end of 2029.
The project covers the stretch from Freedom Square (Vabaduse väljak) in the city center to the Pärnu mnt viaduct to the south, and will be carried out in phases. The city has already completed several major roadworks projects in 2026, including the Hipodroomi intersection in the Kristiine district.
Timeline
Deputy Mayor Kristjan Järvan (Isamaa) told ERR that design firm K-Projekt is finalizing the main design. A building permit application is due within weeks, and a construction tender is planned for the first quarter of next year. Contracts are expected to be signed in summer or early autumn 2027.
Järvan said the order of work will be settled during the tender and site preparation, taking into account traffic flow, access to properties and the sequence of utility works. He described the project as an extensive reconstruction of street space and utility networks.
Design changes
The preliminary designs have been amended to include a right-turn lane from Suur-Ameerika tänav onto Pärnu maantee and a new crosswalk near the Roosikrantsi intersection. Trams and buses will move to center-road stops just before the Liivalaia–Suur-Ameerika intersection and opposite Tallinna Ühisgümnaasium high school, just ahead of the start of the viaduct.
Järvan said the city wants to start as early as possible next year to shorten the period in coming years when traffic is disrupted on several main arteries at once.
"Main Street" project set aside
After this stage, the city will prioritize overhauling the Pärnu mnt viaduct rather than advancing the long-stalled "Main Street" (Peatänav) project, which would have extensively redeveloped nearby Estonia pst. According to Järvan, the city picks projects where the street or its utility networks are worn out, and Main Street does not currently meet that test. Skipping it also avoids changes to the wastewater system that would have put upward pressure on water rates in the capital.