BalticsPublished: 29 November 2026 at 19:31

Estonia completes Baltic region's most powerful hybrid energy park

A hybrid park combining a 77.5 MW solar farm with the Baltics' largest battery system has been completed near Lihula, Estonia. About 110 million euros was invested in the project.

Foto: BNN

A hybrid energy park, the most powerful in the Baltic states, has been completed near Lihula in Estonia. It combines a 77.5 MW solar farm with the largest battery storage system in the Baltics, rated at 55 MW with a capacity of 250 MWh. Such a setup allows generated electricity to be stored and fed into the grid when demand is higher. Estonian energy company Evecon and investment firm Mirova together invested about 110 million euros in the project.

The park is built around the Kirikmäe solar farm, which became the largest in the Baltic states when construction finished in October 2024. Mirova is an asset management company affiliated with Natixis Investment Managers and specialising in sustainable investment.

Why storage matters

Evecon chief Karl-Joonatan Kvell says that alongside renewable generation, energy storage is playing a growing role in Estonia's power system. A solar farm produces electricity when the sun shines, but that does not always coincide with peak demand and the highest prices. The battery system can store energy during lower-price hours and supply it to the grid as demand rises. Batteries can also respond quickly to grid changes and provide frequency regulation reserves, which help keep the system stable.

Raphaël Lance, Mirova's global head of private assets management, stresses that combining generation and storage strengthens Europe's energy independence.

Construction and contract

Construction of the battery system began in January 2026. The work was carried out by WiSo Engineering, which also delivered the Kirikmäe solar farm. Its head, Risto Virveste, says construction of the system is complete and the final technical checks are currently being wrapped up. Battery systems built with the company's involvement total almost 700 MWh in capacity.

The hybrid park was developed by Mirova and Evecon through their joint venture, Baltic Renewable Energy Platform. It has signed a ten-year power purchase and flexibility agreement with German energy company Pure Energy. The deal covers electricity generated at the Kirikmäe, Imavere and Lohu Mets solar parks as well as the newly built battery system. It is the first contract of its kind in the Baltics to combine the sale of renewable electricity with market-based optimisation of battery operation.

Swedbank supported the project with almost 85 million euros in financing.