Building Small Structures in Latvia: What Eased Rules Mean for Greenhouses, Canopies and Saunas
Latvia has simplified the process for building small outbuildings such as greenhouses, sheds and saunas, but there is no blanket rule that small structures can go up without permission. The procedure depends on the building's size, placement and the plot's regulations.

Latvian homeowners planning a greenhouse, shed, canopy or small sauna have in recent years faced fewer paperwork and approval requirements. However, the State Construction Control Bureau (BVKB) and municipal building authorities stress that this does not mean small buildings can be erected without any permission: the applicable procedure depends on the specific project and the plot.
What has changed
The Ministry of Economics explained that since 1 August 2025, construction design documentation has been abolished for certain small buildings, both in and outside cities. In cities, the condition is that the plot allows construction of a house with one or two apartments. The relief does not apply in protected cultural monument areas. From the start of 2026, the notification procedure applies more widely: for first-group residential buildings, auxiliary buildings and non-residential agricultural buildings, there is in certain cases no longer a need to wait for a decision from the building authority.
BVKB's example: for a single-storey greenhouse with a 20 square metre footprint, intended for the family's own needs and located outside a city and a cultural monument territory, neither construction design documentation nor building authority approval is required.
What counts as a small building
The Dobele municipality building authority explains that a small building is a single-storey structure with a footprint of up to 25 square metres. For a building with foundations, the area is measured along the foundation outline; for one placed on a prepared base or foundation blocks, along the outer walls. Usable interior floor area and building footprint are not the same thing.
What else to check
Municipalities remind owners about building density, distances between buildings, protection zones, fire safety distances and third-party rights. Riga's explanation mentions a four-metre distance from the plot boundary, which can be reduced in certain cases with the neighbour's consent. In Riga, the first step is to check zoning on the GeoRiga map.
For a single-storey auxiliary building with a footprint above 25 but no more than 60 square metres, a notification with the required documents usually has to be submitted through the Building Information System (BIS).
Registration
Since 6 January 2026, a unified building registration process has operated, under which data on new construction passes from BIS to the cadastre and land register in sequence. The State Land Service reported that in the first month, 52 processes related to simplified renovation or reconstruction of apartments were completed, with the service received in five working days on average.