Narva line station rebuilds planned through 2028
Estonian state railway infrastructure company Eesti Raudtee has launched a procurement for rebuilding the Auvere, Vaivara and Narva stations in Ida-Viru County. Construction is due to start in spring and finish by the end of November 2028.

Eesti Raudtee, Estonia's railway infrastructure company, has opened a procurement to find a contractor for reconstruction of the Auvere, Vaivara and Narva railway stations in Ida-Viru County, in the country's northeast. Auvere station will be eliminated, while the Vaivara station building will be renovated. The work is the last stage of upgrading the Tallinn–Narva line for faster passenger trains.
Imre Reipõld, head of construction services at Eesti Raudtee, said the procurement winner is expected to be chosen in the first half of next year. Construction should begin in spring and be completed by the end of November 2028. The company has not disclosed the estimated cost, and the work will be done in stages.
What is planned at the stations
Passenger trains last stopped at Auvere in 2012, and the station building and platforms have since been demolished. The switches will now be removed and the station will cease to exist. At Vaivara, the station building is to be reconstructed along with railway work, most of it linked to electrification of the line. In Narva, the station layout will be redesigned and infrastructure built so that passenger trains can reach the platform faster.
Earlier work
Track straightening and major rehabilitation of the Tapa–Narva section, underway since 2022, is now complete. Its cost exceeded €16 million, with the European Union providing 85 percent of the funding. The work makes it possible to raise the maximum speed of passenger trains from 135 to 160 kilometers per hour.
An express train trip between Tallinn and Narva currently takes two hours and 13 minutes. Once all work is finished and operating permits are in place, the journey is expected to shorten to one hour and 50 minutes from June next year.
Reipõld said no curves remain to be straightened on the Narva line. Electrification and traffic management work on the Tapa–Narva section will continue. The overhead contact line has been completed all the way to Narva, while work continues on freight traction substations in Püssi and Oru. Reconstruction of the signaling system on the section will begin next year, proceed section by section and finish in 2028.